Obtain the E-ACTCLD-23 PDF Dumps Get 100% Outcomes Exam Questions For You To Pass [Q87-Q107]

Share

Obtain the E-ACTCLD-23 PDF Dumps Get 100% Outcomes Exam Questions For You To Pass

E-ACTCLD-23 Exam Dumps Contains FREE Real Quesions from the Actual Exam


SAP E-ACTCLD-23 Exam Syllabus Topics:

TopicDetails
Topic 1
  • Provide an overview of content, tools and methodology elements of SAP Activate Solution Implementation Framework
  • Agile Project Planning
Topic 2
  • Describe concepts, artefact flows, accelerators
  • Introduction to SAP Cloud ALM for Implementation
Topic 3
  • Introduction to SAP Cloud ALM for Operations, Monitoring Business Processes
  • User story mapping and construction of backlog
Topic 4
  • Describe concepts, landscape overview and specifics in Workstreams related to implementing SAP S
  • 4HANA Cloud
  • Agile Project Delivery
Topic 5
  • Define factors influencing SAP Activate, its purpose and place among other frameworks
  • New Implementation SAP S
  • 4HANA Cloud

 

NEW QUESTION 87
What solution operations framework can customers use to create a joint business and IT organization?

  • A. SAP Activate
  • B. Customer Center od Expertise
  • C. SAP Roadmap Explorer
  • D. Business Transformation Management Methodology

Answer: A

 

NEW QUESTION 88
What is a key characteristic of SAP Activate for new implementations of S/4HANA cloud edition? Please choose the correct answer.

  • A. Design-based
  • B. Waterfall approach
  • C. Limited involvement of business stakeholders
  • D. Start with executable content

Answer: D

 

NEW QUESTION 89
How do you gain access to the SAP Activate Methodology Jam site?

  • A. Send e-mail to SAP contact address
  • B. Register on SAP Service Marketplace
  • C. Join SAP S/4HANA group on SAP Community Network
  • D. Submit e-mail address via online form

Answer: D

 

NEW QUESTION 90
What are some of the key topics covered in the Customer Team Enablement workstream? 3 correct answers

  • A. project sourcing approach
  • B. planning skills
  • C. technical expertise
  • D. project management
  • E. solution expertise

Answer: C,D,E

 

NEW QUESTION 91
In which phase do you run the user acceptance test?

  • A. Deploy
  • B. Realize
  • C. Final Preparation
  • D. Build and Test

Answer: B

 

NEW QUESTION 92
Which of the following are available in the initial SAP Methodologies JAM Page? There are 2 answers to this question.

  • A. Accelerators
  • B. Summary
  • C. Task description
  • D. Roadmaps

Answer: A,D

 

NEW QUESTION 93
In which phase of the SAP Activate methodology does the team complete the Cut-over Rehearsal?

  • A. Deploy
  • B. Prepare
  • C. Explore
  • D. Realize

Answer: A

 

NEW QUESTION 94
What are some of the key topics covered in the Customer Team Enablement workstream? Note: There are 3 correct answers to this question.

  • A. Planning skills
  • B. Project management
  • C. Technical expertise
  • D. Solution expertise
  • E. Project sourcing approach

Answer: B,C,D

 

NEW QUESTION 95
What did the order processing agent Rafael find out with his root cause analysis? Note: There are 2 answers to this question.

  • A. All sales order items with a credit block had been sold to the same customer.
  • B. A large number of sales order items recently created require urgent next-day delivery.
  • C. Payments for sales items have been received from customer AB Logistics Ltd. in SAP S/4HANA Cloud, but they have not yet been cleared.
  • D. Janet, the process manager, had recently been checking the "Sales Documents with Credit Block KPI".

Answer: A,B

 

NEW QUESTION 96
What are two important approaches, based on the Control Center concept that SAP proposes to use for streamlined implementation and operations within Premium Engagements? There are 2 correct answers to this question.

  • A. Run SAP Like a Factory
  • B. Always Connected
  • C. Intelligent Enterprise
  • D. Build SAP Like a Factory

Answer: A,D

 

NEW QUESTION 97
What do you do during post cutover?

  • A. Perform Technical System Test
  • B. Conduct Organizational Readiness Check
  • C. Setup Operational Support
  • D. Perform the Verification Session of the SAP Going Live Check

Answer: D

 

NEW QUESTION 98
Which of the following is not a Phase in the SAP Activate Methodology?

  • A. Deploy
  • B. Discover
  • C. Prepare
  • D. Go-Live & Support
  • E. Explore
  • F. Realize

Answer: D

 

NEW QUESTION 99
What can you see in the process content viewer?

  • A. Business user roles
  • B. Business process value flows
  • C. SAP Activate tasks
  • D. Business process models

Answer: B

 

NEW QUESTION 100
The hypercare period is part of which phase?

  • A. Deploy
  • B. Explore
  • C. Go-Live
  • D. Realize

Answer: A

 

NEW QUESTION 101
What tool do you use to configure an SAP Business Suite on-premise solution? Please choose the answer.

  • A. ABAP Workbench
  • B. Expert Configuration
  • C. Configuration Composer
  • D. SAP Implementation Guide

Answer: D

 

NEW QUESTION 102
How can the project manager help to keep momentum in the project and help to keep the customer involved?

  • A. Walk through the solution processes with the stakeholders
  • B. Increase the number of Q-Gates
  • C. Add customer resources to the project to reduce the need for formal training
  • D. Leverage agile cycles to build and test the solution

Answer: C,D

 

NEW QUESTION 103
What are some core objectives of business process monitoring? 2 correct answers

  • A. to increase business process execution quality
  • B. to provide reverse business process analysis
  • C. to provide transparency over end-to-end processes
  • D. to provide process update and change feedback

Answer: A,C

 

NEW QUESTION 104
Your project is performing some high-level planning for a System Conversion journey from SAP Business Suite to SAP S/4HANA on-premise edition.
What is the sequence of selected key deliverables across the project phases? Please choose the answer.

  • A. Code Adjustment
  • B. Code Adjustment
  • C. Detailed system Assessment
  • D. Production Readiness Check
  • E. Production Readiness Check
  • F. Production Readiness Check
  • G. Detailed System Assessment
  • H. Code adjustment
  • I. 4th option
  • J. 2nd option
  • K. Validation of Migration
  • L. Validation of Migration
  • M. Detailed system Assessment
  • N. Production Readiness Check
  • O. Validation of Migration
  • P. Validation of Migration
  • Q. Detailed system Assessment
  • R. 3rd option
  • S. Code Adjustment
  • T. 1st option

Answer: M

 

NEW QUESTION 105
What is the difference between the "system conversion" and the "new implementation OF SAP S/4HANA transaction path.
There are 2 option to this question.

  • A. In the realize phase, custom code is adjusted rather than developed for system conversion
  • B. There are different upgrade cycles
  • C. In the realize phase, data is converted and not migrated for system conversion
  • D. SSCUI's are used in system conversion for configuring SAP S/4HANA through the manage Your solution app

Answer: A,C

 

NEW QUESTION 106
What capabilities does SAP API Business Hub provide to help you select integration options for your project?
3 correct answers

  • A. Advice on selecting scope items in SAP Best Practice Explorer
  • B. Pre-packaged integration
  • C. Integration with IDE and code generation
  • D. Sandbox for testing API's
  • E. Recommendations on using integration bus (SAP Process Orchestration or SAP Integration Suite)

Answer: B,D,E

 

NEW QUESTION 107
......

Use Real SAP Achieve the E-ACTCLD-23 Dumps - 100% Exam Passing Guarantee: https://lead2pass.troytecdumps.com/E-ACTCLD-23-troytec-exam-dumps.html